Amor Village Library – Phase II Budget

The following tables show a breakdown of the full cost of completing Phase II of the Amor Community Library project. The total cost of the roof and the walls is UGX 49 747 000 (~USD 14 400 / ~EUR 12 700). Thanks to a generous grant of CAD 6 000 from the MacEwan University Global Education Fund, the remaining cost is roughly USD 10 000 / EUR 8 900!

We are currently working to meet this cost through a fundraiser hosted at Generosity.com.

A Library to Lift Up a Community

Walls

ItemQuantityCost (UGX)Cost (USD)
[converted]
Cost (EUR)
[converted]
Timbers1141 140 000301.59260.36
Nails40 kg1 600 000423.28365.42
Iron bars652 251 000595.50514.09
Rings80400 000105.8291.35
Binding wires2 bundles140 00037.0431.97
Aggregates8 trips2 240 000592.59511.58
River sand20 trips3 200 000846.56730.83
Cement258 bags8 256 0002,184.131,885.54
Bricks10 000Provided by the community
Poles50250 00066.1457.10
Ropes3015 0003.973.43
Water supply1 000 jerrycans400 000105.8291.35
Labor cost3 500 000925.93799.35
TOTAL23 392 0006,188.385,342.37

Roof

ItemQuantityCost (UGX)Cost (USD)
[converted]
Cost (EUR)
[converted]
Timbers115611 560 0003,058.212,640.13
Iron sheets2978 910 0002,357.152,034.91
Nails53 kg2 405 000636.25549.27
Roofing nails50 kg300 00079.3768.52
Iron Ridges40480 000126.98109.62
Iron Valleys26390 000103.1789.07
Hoop iron8 rolls440 000116.40100.49
Transport310 00082.0170.80
Labor cost1 560 000412.70356.28
TOTAL26 355 0006,972.256,019.08