Amor Village Library – Phase II Budget

The following tables show a breakdown of the full cost of completing Phase II of the Amor Community Library project. The total cost of the roof and the walls is UGX 49 747 000 (~USD 14 400 / ~EUR 12 700). Thanks to a generous grant of CAD 6 000 from the MacEwan University Global Education Fund, the remaining cost is roughly USD 10 000 / EUR 8 900!

We are currently working to meet this cost through a fundraiser hosted at Generosity.com.

A Library to Lift Up a Community

Walls

ItemQuantityCost (UGX)Cost (USD)
[converted]
Cost (EUR)
[converted]
Timbers1141 140 000294.68254.83
Nails40 kg1 600 000413.58357.66
Iron bars652 251 000581.86503.18
Rings80400 000103.4089.42
Binding wires2 bundles140 00036.1931.30
Aggregates8 trips2 240 000579.01500.72
River sand20 trips3 200 000827.16715.32
Cement258 bags8 256 0002,134.081,845.53
Bricks10 000Provided by the community
Poles50250 00064.6255.88
Ropes3015 0003.883.35
Water supply1 000 jerrycans400 000103.4089.42
Labor cost3 500 000904.71782.38
TOTAL23 392 0006,046.555,229.00

Roof

ItemQuantityCost (UGX)Cost (USD)
[converted]
Cost (EUR)
[converted]
Timbers115611 560 0002,988.122,584.10
Iron sheets2978 910 0002,303.131,991.72
Nails53 kg2 405 000621.66537.61
Roofing nails50 kg300 00077.5567.06
Iron Ridges40480 000124.07107.30
Iron Valleys26390 000100.8187.18
Hoop iron8 rolls440 000113.7398.36
Transport310 00080.1369.30
Labor cost1 560 000403.24348.72
TOTAL26 355 0006,812.455,891.34

Leave a Reply

Your email address will not be published. Required fields are marked *