Amor Village Library – Phase II Budget

The following tables show a breakdown of the full cost of completing Phase II of the Amor Community Library project. The total cost of the roof and the walls is UGX 49 747 000 (~USD 14 400 / ~EUR 12 700). Thanks to a generous grant of CAD 6 000 from the MacEwan University Global Education Fund, the remaining cost is roughly USD 10 000 / EUR 8 900!

We are currently working to meet this cost through a fundraiser hosted at Generosity.com.

A Library to Lift Up a Community

Walls

ItemQuantityCost (UGX)Cost (USD)
[converted]
Cost (EUR)
[converted]
Timbers1141 140 000317.64272.67
Nails40 kg1 600 000445.81382.70
Iron bars652 251 000627.19538.41
Rings80400 000111.4595.68
Binding wires2 bundles140 00039.0133.49
Aggregates8 trips2 240 000624.13535.78
River sand20 trips3 200 000891.61765.40
Cement258 bags8 256 0002,300.361,974.74
Bricks10 000Provided by the community
Poles50250 00069.6659.80
Ropes3015 0004.183.59
Water supply1 000 jerrycans400 000111.4595.68
Labor cost3 500 000975.20837.16
TOTAL23 392 0006,517.695,595.09

Roof

ItemQuantityCost (UGX)Cost (USD)
[converted]
Cost (EUR)
[converted]
Timbers115611 560 0003,220.952,765.02
Iron sheets2978 910 0002,482.592,131.17
Nails53 kg2 405 000670.10575.25
Roofing nails50 kg300 00083.5971.76
Iron Ridges40480 000133.74114.81
Iron Valleys26390 000108.6793.28
Hoop iron8 rolls440 000122.60105.24
Transport310 00086.3874.15
Labor cost1 560 000434.66373.13
TOTAL26 355 0007,343.276,303.81